VGF UTLIZATION STATEMENT & PHYSICAL PROGRESS OF NEGG PROJECT FY 2023-24
(Amount in Rs crore)
IGGL | ||||
Month |
Scheduled CAPEX |
Actual CAPEX |
VGF @ 60 % of capex |
Physical Progress % |
April’23 |
101 | 37 | 22 | 71.71 |
May’23 |
101 | 33 | 20 | 73.92 |
June’23 |
101 | 129 | 77 | 75.07 |
July’23 |
122 | 68 | 41 | 75.77 |
August’23 |
122 | 21 | 12 | 76.15 |
September’23 |
122 | 169 | 102 | 76.62 |
October’23 |
363 | 5 | 3 | 77.00 |
November’23 |
363 | 70 | 42 | 77.43 |
December’23 |
363 | 191 | 115 | 77.92 |
January’24 |
414 | 64 | 38 | 78.47 |
February’24 |
414 | 112 | 67 | 79.16 |
March’24 |
414 | 228 | 137 | 80.40 |
Total |
2,999 | 1,126 | 676 |
VGF UTLIZATION STATEMENT & PHYSICAL PROGRESS OF NEGG PROJECT FY 2022-23
(Amount in Rs crore)
IGGL | ||||
Month |
Scheduled CAPEX |
Actual CAPEX |
VGF @ 60 % of capex |
Physical Progress % |
April’22 |
232 |
65 |
39 |
45.03 |
May’22 |
232 |
68 |
41 |
47.68 |
June’22 |
232 |
166 |
99 |
49.22 |
July’22 |
150 |
109 |
66 |
50.33 |
August’22 |
150 |
117 |
70 |
52.43 |
September’22 |
150 |
117 |
70 |
53.94 |
October’22 |
307 |
142 |
85 |
54.96 |
November’22 |
307 |
6 |
4 |
59.25 |
December’22 |
307 |
423 |
254 |
61.31 |
January’23 |
309 |
208 |
125 |
64.19 |
February’23 |
309 |
323 |
194 |
66.54 |
March’23 |
309 |
575 |
345 |
70.01 |
Total |
2,997 |
2,321 |
1,392 |
|
VGF UTLIZATION STATEMENT & PHYSICAL PROGRESS OF NEGG PROJECT FY 2021-22
(Amount in Rs crore)
IGGL |
||||
Month |
Scheduled CAPEX |
Actual CAPEX |
VGF @ 60 % of capex |
Physical Progress % |
April’21 |
36 |
36 |
21 |
16.95 |
May’21 |
21 |
21 |
13 |
17.91 |
June’21 |
144 |
123 |
74 |
18.79 |
July’21 |
16 |
36 |
22 |
19.30 |
August’21 |
19 |
41 |
25 |
19.93 |
September’21 |
120 |
171 |
102 |
20.13 |
October’21 |
145 |
19 |
11 |
21.57 |
November’21 |
178 |
281 |
168 |
27.56 |
December’21 |
249 |
226 |
136 |
31.71 |
January’22 |
137 |
108 |
65 |
36.16 |
February’22 |
200 |
230 |
138 |
38.84 |
March’22 |
289 |
266 |
159 |
42.94 |
Total |
1,553 |
1,556 |
934 |
42.94 |