VGF UTLIZATION STATEMENT & PHYSICAL PROGRESS OF NEGG PROJECT FY 2023-24
(Amount in Rs crore)
IGGL | ||||
Month |
Scheduled CAPEX |
Actual CAPEX |
VGF @ 60 % of capex |
Physical Progress % |
April’23 |
101 | 37 | 22 | 71.71 |
May’23 |
101 | |||
June’23 |
101 | |||
July’23 |
122 | |||
August’23 |
122 | |||
September’23 |
122 | |||
October’23 |
363 | |||
November’23 |
363 | |||
December’23 |
363 | |||
January’24 |
414 | |||
February’24 |
414 | |||
March’24 |
414 | |||
Total |
2,999 | 37 | 22 |
Note: Capex & VGF figures given above are provisional